Day One: Protecting wall monuments and pews ahead of the scaffolding erection, Monday, 6th February.
![]() |
|
![]() |
![]() |
![]() |
![]() |
| Day Four: All wrapped up and ready to start, Thursday, 10th February | |
![]() View from the North Porch |
![]() The organ |
![]() View of the nave towards the east window |
![]() The smoke damaged roof space |
| Day Fifteen: The Scaffolding is up Monday, 21st of February | |
![]() |
![]() |
![]() |
![]() |
| Day Twenty Six: Contractors huts
have been installed and restoration proceeds apace, 4th March. |
|
|
|
|
|
|
|
|
|
|
| Day Thirty Two Architects Photos of the cleaning process 10th March | |
|
|
|
| Day Forty Four the painstaking process of cleaning and restoration, photos by Emma Norris, Conservator 22nd March | |
![]() monument 33 partial clean |
Monument 15 before cleaning |
|
Monument 15 after cleaning |
Monument 15 after retouching to lettering |
![]() Monument 37 retouching to lettering |
Cleaning and application of wood reviver to reredos |
|
Removing latex and cleaning of purbeck columns |
|
| Day 92 - 15th May The scaffolding has been removed from the nave. | |
|
The walls are a gleaming white. |
Cleaning of the font is complete. |
|
|
|
| Much work remains for the electricians and carpenters to complete. | |
|
The restored monuments are being revealed. |
Organ pipes have been removed for cleaning. |
| Day 96 19th May | |
|
Checking that the cleaned memorials are still clean now that the decorators are finished in the Nave |
The carpenter working on the damaged pew platform |
| Day 102 25th May | |
|
|
|
| The final areas of floor are latexed | |
|
|
|
| Emma Norris has been back to give the purbeck marble columns another coating of wax and to check on all the monuments & memorials now that the scaffolding has been taken away | |
|
Cunnings Recording Associates have been in , repairing the sound system |
Neill Fraser, our wonderful site manager |
| Day 154 5th June | |
| Mearly done! Work on cleaning the organ continues: | |
|
|
|
|
|
|
|
|
|
View photos of the Fire Damage on January 16th
Day One
Day Four
Day Fifteen
Day Twenty Six
Day Forty Four
Day ninety two
Day ninety six
Day One hundred and two
Day One hundred and fifty four
|
Latest Updates
|
"TimeCapsule" ![]() Found under the eaves during restoration in April Read the full text HERE |